Compensate, don’t rebuild: The faster way to resolve LV power quality constraints

Solar, batteries, EV chargers and heat pumps are pushing LV feeders past voltage, imbalance and harmonic limits. Single-phase connections load the three phases unevenly. Neutral current rises, voltage drifts out of limits at the end of the feeder, and customers see curtailment and complaints, often while the transformer still has spare capacity.

The traditional fix replaces the network: split the feeder, pull down small conductors, poles and transformers, and install larger ones. Each project is a custom civil job with:

  • Site-specific design for every location, so cost and lead time are set by the site.
  • Multiple approvals, including civil works approvals, before construction starts.
  • Crews and plant scheduled for a construction programme measured in days on site.
  • A planned outage for the customers on that LV network, with notification periods to meet.

Augmentation adds capacity whether or not capacity is what limits the feeder.

The EcoVAR Alto is a 40 kVA pole-mounted LV D-STATCOM. It connects in parallel with the existing network and does not carry feeder load. It measures each phase and:

  • Moves active power between phases to balance load and reduce neutral current.
  • Injects or absorbs reactive power to hold voltage within limits.
  • Filters harmonic currents from inverters and other non-linear loads.

The installation design is the same at every site: one pole-mounted unit connected to a 4-wire, 3-phase LV circuit. Installation takes under 2 hours, and the unit can be connected without interrupting supply. There are no civil works and no planned outage for customers.

 AugmentationEcoVAR
Scope of workReplace conductors, poles and/or transformerAdd one pole-mounted unit in parallel
DesignCustom design for each siteSame installation design at every site
ApprovalsNetwork, civil and customer notificationStandard network approval for a standard asset
Time on siteDays of constructionUnder 2 hours
Customer outagePlanned outage requiredNone
Cost basisSet by site conditions; known after designStandard unit and installation; known up front
What it fixesAdds capacityAdds PV Hosting Capacity, and corrects Imbalance, voltage and harmonics on the existing network.

Because each EcoVAR is a standard unit with a standard installation, cost per constraint is known before work starts and is lower than rebuilding the network. A fixed capital budget resolves more LV constraints, sooner. Existing poles and wires carry more energy, and more customers can connect and export solar without a network rebuild.


EcoJoule Energy designs and manufactures LV D-STATCOMs and battery energy storage systems in Brisbane, Australia. Its technology lets the benefits of the energy transition reach all users of the distribution network by making full use of existing poles and wires.